Arena construction monitor back with regular reports, says arena is on schedule

The Barclays Center is still on schedule, says Merritt & Harris, construction consultant for the Barclays Center arena bond trustee, which is back to a more regular timetable after skipping two reports in the fall.

The most intriguing element of the Arena Site Observation Report released yesterday, dated 1/16/13 and based on a visit on 11/29/12, was the delayed inclusion of documents regarding belatedly-revealed problems with the arena facade and bolts. (See separate post.)

Nearing completion

The arena is on schedule for final completion of 2/28/13, according to the report, with 102 workers doing punch list work on non-event days.

As of 11/30/12, 97.1% of the budget ($510.7 million) for the arena design/build contract had been spent. Similarly, 97.1% of the budget ($57.9 million) for the transit connection had been spent.

By contrast, only 86.4% of the $3.7 million budget for site work had been spent.

Arena construction progress chart: January 2013 report
(compare with previous charts, based on different elapsed time)

Transit connection construction progress chart: January 2013 report
(compare with previous charts, based on different elapsed time)



emergency cash loan

Up To $1500 Quick Loan Online. No Hassle. Fast Instant Approval. Withdraw Your Cash. Get Cash Fast Today!

Rating of emergency cash loan




Get Online Application at online payday loans.

Tidak ada komentar:

Posting Komentar

Copyright © 2014. Gorjao Business - All Rights Reserved
Home | About loan | new loan | loan pathner